Asphalt Rolling and Finishing on Padma Bridge

The Padma Multipurpose Bridge is a multipurpose road-rail bridge across the Padma River, the main distributary of the Ganges, under construction in Bangladesh.

The first Asphalt rolling of the Padma multipurpose bridge began on 13th July 2021 by Padma Multipurpose Bridge Project (MBEC-5).

Asphalt work was completed at the 40th end of the Janjira end of the Padma Bridge. First, a layer of waterproof bitumen (10 m wide and 60 m long) is laid on the slab of the bridge before pouring the pitch. As a result, the slabs will not be damaged by rainwater.

A Paver / Asphalt finisher, 2 drum rollers, 2 tire rollers, 2 tandem rollers, and 4 dump trucks were brought here to complete this work.